Adani Energy rises after wining Rs 2,800 crore transmission project in Gujarat
Adani Energy Solutions advanced 2.55% to Rs 836.05 after the company said that it has won a power transmission project worth Rs 2,800 crore in Gujarat.

This project will supply green electrons for the production of Green Hydrogen and Green Ammonia in Mundra.

Scheduled for completion within 36 months, the project involves upgrading the Navinal (Mundra) electrical substation with two large 765/400kV transformers.

Additionally, a 75 km long 765kV double-circuit line will be constructed to connect this substation to the Bhuj substation.

The project will see the addition of 150 circuit kilometers (cKM) of transmission lines and 3,000 MVA of transformation capacity to AESL’s overall transmission infrastructure, taking them to 25,928 cKM and 87,186 MVA, respectively.

AESL won the project under the Tariff Based Competitive Bidding (TBCB) mechanism. The project SPV was formally transferred to AESL on 20 March 2025.

"This is AESL’s 6th order win this fiscal year, taking its orderbook to approximately Rs 57,561 crore,” the company said.

Adani Energy Solutions (AESL), part of the Adani portfolio, is a multidimensional organization with presence in various facets of the energy domain, namely power transmission, distribution, smart metering, and cooling solutions.

The company reported 72.9% jump in consolidated net profit to Rs 561.78 crore in Q3 FY25 as compared with Rs 324.90 crore in Q3 FY24. Revenue from operations jumped 27.78% YoY to Rs 5,830.26 crore in Q3 FY25.

Previous News
  Stock Alert: Adani Energy Solutions, Tech Mahindra, Jupiter Wagons, Cyient, United Breweries
 ( Market Commentary - Stock Alert 26-Jul-24   08:44 )
  Market hits fresh life high; Nifty scales above 25,300
 ( Market Commentary - Mid-Session 02-Sep-24   09:32 )
  Indices drift higher in early trade; Breadth strong
 ( Market Commentary - Mid-Session 26-Jul-24   09:35 )
  Adani Energy Solutions signs SPA to acquire Mahan Transmission
 ( Corporate News - 27-Mar-25   14:58 )
  Adani Energy Solutions reports consolidated net loss of Rs 823.92 crore in the June 2024 quarter
 ( Results - Announcements 26-Jul-24   07:31 )
  Stock Alert: Auto firms, Adani Energy Solutions, Fortis Healthcare, Century Textiles, NBCC, Emami
 ( Market Commentary - Stock Alert 02-Sep-24   08:35 )
  Adani Transmission to hold AGM
 ( Corporate News - 26-Jun-23   12:32 )
  Adani Energy Solutions undertakes 7GW Khavda IVA Power Transmission project
 ( Corporate News - 02-Sep-24   10:33 )
  Adani Energy Solutions Ltd spurts 1.66%, rises for third straight session
 ( Hot Pursuit - 10-Jun-24   13:05 )
  Adani Transmission wins Golden Peacock Environment Management Award
 ( Corporate News - 12-Jul-23   13:04 )
  Adani Transmission to acquire Essar's 400 kV Mahan-Sipat transmission project
 ( Corporate News - 04-Jun-22   13:32 )
Other Stories
  Kamat Hotels Q4 PAT surges 412% YoY to Rs 11 cr
  26-Apr-25   16:21
  Bank of Maharashtra Q4 PAT climbs 23% YoY to Rs 1,493 crore
  26-Apr-25   15:34
  Oracle Financial Services Software Q4 PAT up 19% QoQ
  26-Apr-25   14:28
  Force Motors Q4 PAT surges 210% YoY to Rs 435 cr; declares dividend of Rs 40/sh
  26-Apr-25   14:02
  L&T Finance Q4 PAT rises 15% YoY to Rs 636 crore
  26-Apr-25   13:31
  RBL Bank PAT drops 81% YoY to Rs 69 crore in Q4 FY25; provisions zoom by 90% YoY
  26-Apr-25   12:12
  Tejas Networks reports dismal Q4 outcome
  26-Apr-25   11:54
  Zydus Life gets 6 observations from USFDA for API plant
  26-Apr-25   11:02
  RIL Q4 PAT rises 6.4% YoY
  26-Apr-25   10:05
  Tata Technologies Q4 PAT climbs 12% QoQ to Rs 189 cr
  25-Apr-25   17:34
Back Top